E1/AS1 Surface Water

Cross-sectional area of external and internal gutters (Figures 15 and 16), downpipe sizes (Table 5) and overflow outlets, with the rainfall intensity from Appendix A.

  • E1/AS1First Edition Amendment 122 Nov 2023

Where E1/AS1 stops applying

1.0.1 lists five things, and any one of them puts a site outside E1/AS1. Nothing below is locked behind them: they are here as a reminder, and the moment one is ticked the verdict says so. Where you are unsure of one, read the note under it; there is nothing to answer first.

The catchment is everything draining to the drainage being designed, not just the roofs, and not the title area. Practical shortcut: if no water flows onto the site from elsewhere, the catchment cannot exceed the site area, so a site under 2500 m² does not trip this. The document does not say whether a large site may be split into independent systems each under 0.25 ha.

Check the LIM report and the council property file, and the council's flood hazard maps (in Auckland, Flood Viewer or GeoMaps: flood plains and flood prone areas). The maps are regional models, not site records, so ask the owner and neighbours as well.

Walk the site, then check the council GIS watercourse layer (including piped and intermittent streams) and the LINZ topo map. 'Adjacent' is not defined; if in doubt, raise it with the BCA.

Compare site levels with the surrounding ground and the road using the council contour or LiDAR layer, or a topographical survey. Council 'flood prone area' layers map depressions that can pond.

Council overland flow path layers map this directly: they show where water flows when the stormwater network is overloaded. They are derived from terrain analysis, not hydraulic modelling, so verify a nearby path against the survey, especially after earthworks.

These pointers are guidance from this tool, not part of E1/AS1. The building consent authority decides whether the evidence is sufficient.

Rainfall intensity

E1/AS1 sizes on the 10% AEP, 10 minute duration intensity for the site (3.2.2). Figures 15 and 16 are drawn for 100 mm/hr, so above that the gutter size read from them is multiplied by I/100; at or below it the figure value is used as read and never reduced (5.1.3).

Your project has no rainfall location or figure yet. Set the Appendix A location in the project (or, where no location fits, an intensity from elsewhere), and every clause that needs it reads the same one.

Set the rainfall location, or an intensity from elsewhere, in the project to size gutters.

Gutter sections and downpipes

Each card is one gutter section and the downpipe at the end of it. 5.1.2 makes a section the length of gutter between a downpipe and the adjacent high point on one side of that downpipe only. One roof area sizes both: Figures 15 and 16 read the gutter from it, and Table 5 reads the downpipe from it.

Remove “RF-1”?

Everything answered about it goes with it.

Set the rainfall location, or an intensity from elsewhere, in the project before this can be sized. Figures 15 and 16 are scaled by the design intensity (5.1.3).

Downpipe

Smallest downpipe
63 mm diameter
Table 5

63 mm diameter

Acceptable Table 5 sizes for 60 m² at 0-25: 63 mm diameter, 74 mm diameter, 100 mm diameter, 150 mm diameter, 65 x 50 rectangular, 100 x 50 rectangular, 75 x 75 rectangular, 100 x 75 rectangular.

Smallest is 63 mm diameter (nominal internal cross-section 3117 mm²). Another downpipe is acceptable if its cross-sectional area is no less than this and it passes a 50 mm diameter sphere.

E1/AS1 Table 5 · E1/AS1 4.2.1

Drains

Each drain run is a below-ground pipe carrying roof water (the downpipes discharge straight into it) and paved-area water through sumps, to the outfall. Pick the sections whose downpipes reach this run rather than adding their areas up again, and the run answers with the smallest pipe that carries them and the flattest gradient that pipe may be laid at.

No drain runs yet.

Sumps

All surface water except that collected directly from a roof enters the drain via a sump. Roof water discharges directly to the drain, not via a sump. Each sump is selected for the area it serves, using the site's 10% AEP intensity.

No sumps yet.

This tool reads E1/AS1 Amendment 12 and reports what it says. It is not a substitute for reading the document, for the judgement of a suitably qualified person, or for the decision of the building consent authority. Rainfall intensities printed in Appendix A were produced by NIWA in December 2019; check for more recent territorial authority data.

building.govt.nz